Irrigation Update 4/26/22
We've begun installing the largest pipe of the main line. This is a 12" diameter pipe that runs from 7 fairway directly to the pump station. This is currently being installed left of 12 tee along the cart path. Once this area is complete, the crews will continue installing an 8" main to the right of 7 fairway, working toward the green complex. They will tap into our existing cast iron main line in 7 fairway so that both the new system and the old system will have water simultaneously.